Comprehensive Improvement Project for the Lower Reaches of Licun River and Zhangcun River in Qingdao Tidal Barrier Gate Project

Located 210 meters upstream from the Licun River estuary, the project has a designed flood verification standard of 100-year recurrence interval, with a maximum discharge capacity of 1,290 m³/s, classified as a Large (Type 2) scale project.

The main construction contents consist of two parts: the main sluice structure and the management area on the right bank floodplain. The main structure includes: upstream bottom protection and blanket, gate chamber, downstream stilling basin apron, energy dissipation apron, riprap anti-scour trench, various side walls (piers), maintenance bridge and access bridge.